Skip to Main Content

Building 600: Home

Building 600 construction underway

New Library and Learning Connection Building Construction

Interior preview of center stairwell

Interior preview of center stairwell

Outdoor patio view

View from the 3rd floor deck

Interior preview from 3rd floor

Interior preview from 3rd floor

Building 600 interior construction

Building 600 interior construction

Building 600 Feb 2024

Update starting Spring 2024

Building 600 South Face

Windows are up on the south side of Building 600

View from building 1700

Side view of Building 600 with paint

Interior Constructoin

Interior Construction

Exterior siding

Exterior Siding

Building 600 progress summer 2023

Building 600 Progress Summer 2023

Building 600 progress taken April 17, 2023

Building 600 progress - April 17, 2023

Exterior materials sample

Sample building exterior

Sample staircase materials

Staircase materials

Concrete pour view from building 1800

Concrete pour view from building 1800 - January 25, 2023

Concrete pour for 2nd floor, January 25, 2023

Concrete pour for 2nd floor - January 25, 2023

Sunsetting behind building 600

Sunsetting Behind Building 600, December 20, 2022

Topping Off Ceremony Beam Placement

Topping Off Ceremony Beam Placement, December 15, 2022

Topping Off Ceremony Beam Installation

Topping Off Ceremony, December 15, 2022

December 9 construction

Construction December 9, 2022

Crane lifting steel beam

Photo courtesy of Michael Stroud of Swinerton - Nov 10 updates

Steel beams from ground level

Photo courtesy of Michael Stroud of Swinerton - Nov 10 updates

Steel structure

Photo courtesy of Michael Stroud of Swinerton - Nov 10 updates

Pipes construction ground level

Photo courtesy of Michael Stroud of Swinerton - Nov 10 updates

Panoramic construction site

Photo courtesy of Michael Stroud of Swinerton - Nov 10 updates

Steel structure November 3rd

Steel structure - November 3, 2022

Crane with steel beam

Crane placing steel beam - November 1, 2022

Beams

Steel beams - November 1, 2022

Crane with steel beam

Crane lifting steel beam - November 1, 2022

Concrete pour crane

Concrete Pour - October 27, 2022

Concrete pour crane folded

Concrete pour completed - October 27, 2022

Concrete pour crane

Photo courtesy of Michael Stroud of Swinerton

Concrete poured in base

Photo courtesy of Michael Stroud of Swinerton

Concrete pour crane library balcony

Photo courtesy of Library Staff

Foundation

Photo courtesy of Michael Stroud of Swinerton

Concrete pour

Photo courtesy of Michael Stroud of Swinerton

Campus Analysis building 600

HMC Architects Building 600 Site Area

Updates

Mind the noise. Construction is underway for the new Library and Learning Connections Building 600.

  • 1/25/23 : Concrete pour
  • 11/1/22 : Steel beams
  • 10/25/22 - 10/27/22: Concrete slab
  • 9/7/22 - 9/12/22: Concrete pour

Current Status of Project:

11/10/22 - The foundation and slab pours have both been completed. In total, the Contractor poured approximately 2100 cubic yards of concrete. A majority of underground utilities have been installed. On November 1st the Steel erection began is expected to be complete around the middle of December. After that, the contractor will start installing the stairs and metal decking.

9/29/22 -  Increment 1 of the project is complete. Increment 1 included the Ground Improvement scope (drilling and installation of 273 piers) and the installation of some of the underground utilities and the removal of a section of the colonnade (between B1600 and B1700). The contractor finished installing the remaining site utilities last week and is now in the middle of excavating for the footings. We expect them to begin installing the rebar for the footings around the middle of next week, then begin pouring the concrete for the footings between 9/9 and 9/12. Around the end of October the slab-on-grade will be poured. After that the next major milestone will be the erection of the structural steel which is expected to start near the beginning of November.

Michael Stroud, DBIA, LEED AP
Senior Project Manager
SWINERTON